Industrial Hall Demolition Spandau
Complete demolition of a former production hall with subsequent site clearing in Berlin-Spandau.

Challenge
The 2,500 m² industrial hall contained asbestos roof panels and contaminated flooring. Despite its size, demolition had to be completed within 6 weeks.
Solution
First, professional hazardous material remediation was carried out according to TRGS 519. Then the hall was systematically demolished using long-reach excavators and sorting grabs.
Result
Completed on schedule in 5 weeks. 92% recycling rate. Site was handed over for construction of a new logistics center.
Project Data
- Longfront-Bagger
- Sortiergreifer
- Radlader
Similar Projects
School DemolitionSchool Building Demolition Pankow
Demolition of a dilapidated Gründerzeit-era brick school building in Pankow to prepare for a modern new school building.
Residential DemolitionSingle-Family Home Demolition Reinickendorf
Complete demolition of a 1960s single-family home with basement and garage in Reinickendorf.
Prefab Building DemolitionPrefab Building Partial Demolition Marzahn
Partial demolition of an 11-story prefab building – demolition of the upper 5 floors with prior hazardous material remediation.
Your Project
Do you have a demolition project?
Contact us for a free consultation and a non-binding fixed-price quote. We will get back to you within 24 hours.